China Jushi FY2003: Projects and construction progress

Named projects, stages, capacities and construction evidence.

Evidence-linked English operating research. The source and stated coverage below define the scope of this version. Source-page links provide optional verification; the English account is intended to stand on its own.

Reporting period ended 2003-12-31 / Filing published 2004-04-06
Content version 4 / 59b77beb0172 / PUBLISHED

Construction and commissioning

The construction ledger is distinct from named expansion lines

The engineering ledger reports CNY 101.41343670 million of additions to construction in progress and CNY 103.63092330 million transferred to fixed assets during 2003. Its opening balance is CNY 11.23954541 million, other transfers CNY 0.00407331 million and closing balance CNY 9.01798550 million. These accounting movements are not the CNY 150.40885720 million of cash paid for long-lived assets in the consolidated cash-flow statement. A ledger column named a 16,000-tonne tank-furnace drawing project records CNY 1.96668184 million opening work, CNY 91.87104436 million of additions and CNY 93.83772620 million transferred to fixed assets, leaving no closing work in that column. Its stated funding is internally raised funds and loans. A separate 10,000-tonne finished-goods warehouse transferred CNY 2.09663715 million to fixed assets. Warehouse capacity is not manufacturing output capacity. The ledger's 16,000-tonne name does not establish identity with the 10,000-tonne Jiujiang upgrade or the 40,000-tonne line in the business discussion. The latter formally started in November 2003 and remained in civil construction when the report described a plan for production within the year; this is not evidence of 2003 commissioning. Project identity and cash allocation remain unassigned where the filing supplies no reliable bridge.

Reported construction carrying-value additions / 2003 / group construction ledger additions
RMB 101,413,436.7
Reported construction transfer to fixed assets / 2003 / group construction ledger transfers to fixed assets
RMB 103,630,923.3

Project developments in FY2003

Jiujiang 10,000-tonne environmental glass fiber line

Open project history

The Jiujiang upgrade used Jushi Group's established 10,000-tonne-per-year alkali-free glass-fiber tank-furnace drawing technology. The report says construction was completed and the furnace ignited on 6 April 2003, followed by formal production on 28 May. Management reports that the line reached its design production capacity during the month of commissioning. This is a management statement about the startup month, not a disclosed measurement of full-year production, sales or sustained annual utilisation. The report calls the line environmental, but this description alone does not quantify energy use or emissions. The project retains its link to the Jiujiang construction-stage disclosure in 2002, while the 2003 commissioning is a separate dated observation.

Jushi Group 40,000-tonne alkali-free glass fiber line

Open project history

The same named 40,000-tonne alkali-free glass fiber tank-furnace drawing upgrade formally started construction in November 2003. At the time of the annual-report discussion it was in civil construction, with production planned within the year. Because this report was issued in 2004, that wording is preserved as a plan from the filing and is not converted into an assertion that production began in 2003. The project is linked to the 2002 preparation-stage disclosure by its implementing company, product and stated capacity.

Annual production capacity
40,000 tonnes/year

Read the complete annual research snapshot

Sources and scope

What this guide establishes

  • This page presents selected business disclosures from the FY2003 full annual report. It is not an exhaustive extraction of every disclosure.
  • Event dates stated in the text may differ from the reporting year. Later events disclosed before filing are identified explicitly; later annual reports are not inserted into this historical account.
  • The Chinese source was translated and compared with the cited pages in separate passes by the same assistant. Independent editorial review and publication approval remain pending.
  • Capacity, production, sales, project budgets and construction expenditure are different measures. Repairs and programme phases are not automatically incremental capacity.
  • All 79 source pages have been read and material selection is mapped across 22 source groups and eight reader questions. Business mix, operating-company scope, growth stages, cash/credit, control, guarantees, historical tax and settlement are explained. Printed-value, identity and contract-reconciliation boundaries remain isolated. Source-use and independent editorial approval remain pending.
FY2003 full annual report ↗