Expansion and construction accounting

Completed lines and the construction ledger

Management reported that the 40,000-tonne alkali-free line began production in August 2004 and the 30,000-tonne medium-alkali line in September, taking total reported glass-fiber capacity above 210,000 tonnes. These late-year start dates limit how much of annual design capacity can be assumed to contribute to that year's output. The borrowing note attributes higher long-term borrowing to Jushi Group's 40,000-tonne alkali-free investment and Jushi Chengdu's 30,000-tonne medium-alkali investment. The consolidated construction ledger began the year at CNY 9.01798550 million, added CNY 644.59292872 million and transferred CNY 644.43492302 million to fixed assets; after CNY 0.08787310 million of other transfers it closed at CNY 9.08811810 million. Capitalised interest of CNY 11.16157339 million is included in the reported additions and transfers, not extra spending to add again. Project 208 transferred CNY 367.49805843 million and project 209 CNY 272.66370526 million to fixed assets, each with no closing construction balance. The filing does not explicitly equate those ledger codes to the two named capacity lines, so the accounting figures are not allocated to either line. Ledger additions and transfers differ from cash capital expenditure, approved project budgets and incremental annual capacity.

Reported construction opening balance / 2004 / consolidated cip opening
RMB 9,017,985.5
Reported construction carrying-value additions / 2004 / consolidated cip additions
RMB 644,592,928.72
Reported construction transfer to fixed assets / 2004 / consolidated cip fixed asset transfers
RMB 644,434,923.02
Reported construction closing balance / 2004 / consolidated cip closing
RMB 9,088,118.1
Reported cip ledger capitalized interest / 2004 / consolidated cip capitalized interest
RMB 11,161,573.39

Project developments in FY2004

30,000-tonne medium-alkali glass fiber line commissioned in 2004

Open project history

The annual investment discussion says a 30,000-tonne annual-capacity medium-alkali glass-fiber tank-furnace drawing line entered production in September 2004 after 156 days of construction. The borrowing note expressly associates the 30,000-tonne medium-alkali investment with Jushi Chengdu. This supports that disclosed operating association, while the report does not supply a precise plant address or equate the line with construction-ledger project 209. Jushi Group held 57% of Jushi Chengdu, and Chengdu entered consolidation for April–December 2004. Management described the line's technology as proprietary and its scale as exceptional; these are attributed claims, not an independently verified world ranking. The medium-alkali product and September start distinguish it from the separate 40,000-tonne alkali-free line commissioned in August. Annual design capacity is not actual 2004 output or evidence of full utilisation.

Annual production capacity / 2004 / glass fiber medium alkali design capacity
30,000 tonnes/year

Jushi Group 40,000-tonne alkali-free glass fiber line

Open project history

The 40,000-tonne annual-capacity alkali-free glass fiber tank-furnace drawing line was completed after a reported 228-day construction period and entered production in August 2004. This completes the sequence of preparation in the 2002 report and civil construction in the 2003 report. The matching decision follows the named alkali-free line and its stated 40,000-tonne scale; it does not merge the separate medium-alkali project commissioned the following month.

Annual production capacity
40,000 tonnes/year

Read the complete annual research snapshot

Sources and scope

What this guide establishes

  • This page presents selected business disclosures from the FY2004 full annual report. It is not an exhaustive extraction of every disclosure.
  • Event dates stated in the text may differ from the reporting year. Later events disclosed before filing are identified explicitly; later annual reports are not inserted into this historical account.
  • The Chinese source was translated and compared with the cited pages in separate passes by the same assistant. Independent editorial review and publication approval remain pending.
  • Capacity, production, sales, project budgets and construction expenditure are different measures. Repairs and programme phases are not automatically incremental capacity.
  • All 79 source pages have been read and material selection is mapped across 19 source groups and eight reader questions. Disclosed projects, business mix, operating-company scope, funding, relationships and historical tax support are explained. Unresolved naming, guarantee and printed-value boundaries remain isolated. Independent editorial review and source-use approval remain pending.