SINOFILINGS / BUSINESS LIBRARY600176 / PUBLISHED
Annual business review / fy2002-selection-closeout-20261007

China Jushi FY2002: Projects and construction progress

Named projects, stages, capacities and construction evidence.

Evidence-linked English operating research. The source and stated coverage below define the scope of this version. Source-page links provide optional verification; the English account is intended to stand on its own.

Reporting period ended 2002-12-31 / Filing published 2003-03-29
Content version 4 / c42abccfc140 / PUBLISHED

Construction and commissioning

Construction ledger names do not identify projects by capacity alone

The 40,000-tonne alkali-free tank-furnace project was in preparatory work: the report says its environmental assessment was approved and its provincial feasibility approval forwarded to the national authority. It does not report this project commissioned in 2002. The new Jiujiang 10,000-tonne environmentally oriented line was under construction, with CNY 25.3892 million investment completed by year end; civil works, equipment orders and technical training were underway. The issuer attributed independently developed waste-fiber remelting technology to this project; that is an issuer technology claim, not an independent performance assessment. The accounting construction ledger separately identifies a 10,000-tonne alkali-free line transferred to fixed assets at CNY 85.41567149 million, a 6,000-tonne yarn technical renovation transferred at CNY 30.89669936 million, and a 16,000-tonne line with CNY 0.71383051 million closing work in progress. It also lists a 9,000-tonne medium-alkali line at CNY 0.66043710 million, and project 207, labeled a 10,000-tonne furnace, at CNY 1.96668184 million. This filing supplies no reliable identity bridge connecting these ledger entries to the narrative Jiujiang project; capacity labels alone cannot support a merge. The 10,000-tonne finished-goods warehouse is storage, not manufacturing capacity. Overall work in progress fell from CNY 122.76213606 million to CNY 11.15166353 million after CNY 27.22237649 million additions, CNY 137.47510786 million fixed-asset transfers and CNY 1.35774116 million other reductions. Accounting transfers do not establish annual output or a simple sum of incremental capacity.

Reported consolidated construction in progress / 2002 / fy2002 consolidated construction ledger
RMB 11,151,663.53
Transferred to fixed assets / 2002 / fy2002 consolidated construction ledger
RMB 137,475,107.86

Project developments in FY2002

Jiujiang 10,000-tonne environmental glass fiber line

Open project history

The 10,000-tonne environmental alkali-free glass fiber project at Jiujiang used Jushi's proprietary technology for returning waste fiber to the furnace. Construction had formally started. Year-end investment was RMB 25.3892 million; civil work on the main workshop and supporting works was under way, together with equipment ordering and technical training. These details describe the technology, scale and construction stage. They do not establish a commissioning date in the 2002 reporting period.

Annual production capacity
10,000 tonnes/year

Jushi Group 40,000-tonne alkali-free glass fiber line

Open project history

Jushi Group was preparing a 40,000-tonne annual-capacity alkali-free glass fiber tank-furnace drawing upgrade. The report records a project team led by the company president, approval of the environmental assessment, and approval and onward submission of the feasibility study. Preparatory work was continuing. Management's description of the project as exceptionally large and advanced is an assessment; these approvals do not mean the line was already producing in 2002.

Annual production capacity
40,000 tonnes/year

Read the complete annual research snapshot

Sources and scope

What this guide establishes

  • This page presents selected business disclosures from the FY2002 full annual report. It is not an exhaustive extraction of every disclosure.
  • Event dates stated in the text may differ from the reporting year. Later events disclosed before filing are identified explicitly; later annual reports are not inserted into this historical account.
  • The Chinese source was translated and compared with the cited pages in separate passes by the same assistant. Independent editorial review and publication approval remain pending.
  • Capacity, production, sales, project budgets and construction expenditure are different measures. Repairs and programme phases are not automatically incremental capacity.
  • All 67 source pages have been read and material content selected under the foreign-investor and industry-research reader rules. Restructuring, products, projects, operating results, working capital, funding, guarantees and related-party exposure are explained; source discrepancies remain explicitly bounded. This closes same-assistant extraction and selection only. Source-use permission and independent editorial approval remain pending.
FY2002 full annual report ↗
Chinese / A-share / Chinese Accounting Standards / Published 2003-03-29
PDF SHA-256: d999bbd22cd37c97d1252b39a449188eea71f8a79efddb2cff4f93d5a68e0af3