After five years of construction, the company declared the Tongxiang headquarters intelligent manufacturing base complete. The report describes the third electronic-fabric line as successfully ignited and producing. This is a programme-level completion disclosure, following earlier records for individual roving and electronic-yarn phases. Statements of global leadership in this passage are management's assessment rather than an independently verified ranking.
At a glance
- Record type
- Project
- Earliest source in this dossier
- FY2016
- Latest source in this dossier
- FY2022
- Company
- China Jushi / 600176
Read the dated construction and operating milestones below. An installation stage or an engineering-progress percentage does not establish actual production. A programme and its component lines may describe the same capacity at different levels.
Location and identification
Exact physical address and coordinates have not yet been verified for this record.
Verified site coordinates: unavailable. No city-centre point is displayed as a plant location.
Connected operating records
These associations are supported by the cited disclosure. A programme or base association does not establish a shared physical footprint.
Associated component
Tongxiang intelligent base: phase I, 150,000-tonne roving line
Reported measurements
Only measurements attached to this record are shown. Values retain their original reporting scope; rows are not summed into an asset total.
| Measure | Value | Period / scope | Source |
|---|---|---|---|
| Base expansion budget | RMB 9,323,477,000 | 2017-12-31whole base expansion / whole base expansion | FY2017, p. 136 |
| Headquarters budget | RMB 700,000,000 | 2017-12-31headquarters component / headquarters component | FY2017, p. 136 |
| Project budget | RMB 1,471,166,700 | 2017-12-31300kt programme phase i / 300kt programme phase i | FY2017, p. 102 |
| Construction-note additions | RMB 66,405,565.64 | 2017-01-01 to 2017-12-31300kt programme phase i / 300kt programme phase i | FY2017, p. 102 |
| Construction-note balance | RMB 67,736,324.25 | 2017-12-31300kt programme phase i / 300kt programme phase i | FY2017, p. 102 |
| Construction-note physical progress | 5 percent | 2017-12-31300kt programme phase i / 300kt programme phase i | FY2017, p. 102 |
The following sections retain the full available English descriptions and their source context. Associated business context describes its named product or base.
FY2022 / Disclosed developments
FY2018 / Disclosed developments
The Tongxiang headquarters intelligent manufacturing base had separate first-phase roving and fine-yarn components in this report: 150,000 tonnes per year of roving and 60,000 tonnes per year of electronic yarn. Both were ignited and put into production. The base is the wider programme, while these are individual product-line components. This relationship allows later reports to update a particular line without replacing the identity or status of the whole base.
FY2017 / Disclosed developments
The proposed new-materials intelligent manufacturing base was located in Tongxiang Economic Development Zone. The five-year plan comprised three alkali-free glass fiber lines and three electronic-yarn-and-fabric lines, with planned annual capacity of 450,000 tonnes of fiber, 180,000 tonnes of electronic yarn and 800 million metres of electronic fabric. Construction was to proceed in phases. These are planned capacities for different products, not operating output already achieved in 2017.
The Tongxiang new-materials intelligent manufacturing base is a phased programme, rather than a single completed line. Management’s five-year plan describes three alkali-free glass-fiber lines and three electronic-yarn and fabric lines, with planned annual capacities of 450,000 tonnes of glass fiber, 180,000 tonnes of electronic yarn and 800 million metres of fabric. The other-matters note puts the production-line expansion investment at CNY 9,323,477,000, including CNY 700 million for a new headquarters building. Separately, the construction table labels phase I as a 300,000-tonne-per-year intelligent glass-fiber programme, with a CNY 1,471,166,700 budget, CNY 66,405,565.64 of current-year additions and CNY 67,736,324.25 remaining in construction. It reports 4.60% budget utilisation and 5% physical progress, financed through own funds and borrowings. The base-wide investment, headquarters component, phase-I construction account and individual later lines are distinct perimeters. The report does not establish that the phase-I label is itself incremental operational capacity at year end.
- Base expansion budget / 2017 / whole base expansion
- RMB 9,323,477,000
- Headquarters budget / 2017 / headquarters component
- RMB 700,000,000
- Project budget / 2017 / 300kt programme phase i
- RMB 1,471,166,700
- Construction-note additions / 2017 / 300kt programme phase i
- RMB 66,405,565.64
- Construction-note balance / 2017 / 300kt programme phase i
- RMB 67,736,324.25
- Construction-note physical progress / 2017 / 300kt programme phase i
- 5 percent
FY2016 / Disclosed developments
An intelligent glass fiber manufacturing base broke ground in May 2016. The report also describes implementation of a manufacturing-execution-system demonstration at a Tongxiang factory. Management intended higher automation, differentiated products and better efficiency. The base investment and the information-system demonstration are related initiatives, not interchangeable commissioning claims. No production start for the new intelligent base is established by this passage.
Sources and scope
What this guide establishes
- Reporting years identify the source filings. Actual event dates are retained in the text and may differ from the reporting year.
- The latest disclosure year for this object is not confirmation of its current operating status. Coverage is selected, not an exhaustive account of every report.
- Capacity, output, sales, construction progress and expenditure are separate measures. Programme and component capacities are not added together.
- Company contact addresses are location leads. They do not establish exact plant boundaries or the footprint of individual projects.
Chinese / A-share / Chinese Accounting Standards / Published 2017-03-21
PDF SHA-256: aa002910e2f04f6c6a30d3195854c189d363d9f2ad18ff831c5e2a2abbb7b4c2
Chinese / A-share / Chinese Accounting Standards / Published 2018-03-20
PDF SHA-256: 2ad4170565636643a4bfb947742953ed6d3adb848eab77a0efadabbf29b605c8
Chinese / A-share / Chinese Accounting Standards / Published 2019-03-21
PDF SHA-256: e2b646f083dd59dce8ab46c7048bccad60c182aa4128cb3461cf115ce26d0c4b
Chinese / A-share / Chinese Accounting Standards / Published 2023-03-21
PDF SHA-256: 96f4ef3e82dabc79b499e469a1631b2c73de628c0343a783defe2a110afe0c4b