The 2025 annual report said the Huai'an 500 MW wind-power project formally started construction by the end of 2025. This is a separate milestone from installation of the electronic-yarn line.
At a glance
- Record type
- Project
- Earliest source in this dossier
- FY2024
- Latest source in this dossier
- FY2025
- Company
- China Jushi / 600176
Recorded English aliases: On February 9, 2025, China Jushi launched the construction for the second phase
Read the dated construction and operating milestones below. An installation stage or an engineering-progress percentage does not establish actual production. A programme and its component lines may describe the same capacity at different levels.
Identity and scope to resolve
The 200 MW supporting-wind entry in the financial note and the 500 MW wind construction project in the narrative have different disclosed scopes. A common Huai'an association does not resolve whether one is a component of the other. They remain separate records.
Location and identification
Exact physical address and coordinates have not yet been verified for this record.
Verified site coordinates: unavailable. No city-centre point is displayed as a plant location.
Connected operating records
These associations are supported by the cited disclosure. A programme or base association does not establish a shared physical footprint.
Supports product or activity
Huai'an 100,000-tonne electronic-grade glass fiber production line
The following sections retain the full available English descriptions and their source context. Associated business context describes its named product or base.
FY2025 / Disclosed developments
FY2024 / Disclosed developments
The 2024 annual report describes a 500 MW wind-power construction project as supporting the Huai'an 100,000-tonne electronic-grade glass fiber line.
Sources and scope
What this guide establishes
- Reporting years identify the source filings. Actual event dates are retained in the text and may differ from the reporting year.
- The latest disclosure year for this object is not confirmation of its current operating status. Coverage is selected, not an exhaustive account of every report.
- Capacity, output, sales, construction progress and expenditure are separate measures. Programme and component capacities are not added together.
- Company contact addresses are location leads. They do not establish exact plant boundaries or the footprint of individual projects.
Chinese / A-share / Chinese Accounting Standards / Published 2025-03-20
PDF SHA-256: 6a70135e3651e1c5aac041ed072d4a8182d54ea459a9321d521de9731c983284
Chinese / A-share / Chinese Accounting Standards / Published 2026-03-20
PDF SHA-256: c71b2130cf3d5d9135b884f732d06767c6d2de03c6f7563920a2fc19ef73347f