The FY2025 important-construction-project note reports a budget of RMB 880,943,600.00 and engineering progress of 100% for this project. RMB 746,121,169.87 was transferred to fixed assets during the year. The row has no closing construction-in-progress amount. Engineering progress, spending against budget, and actual output are different measures. A blank closing cell is retained as a blank and is not entered as a numeric zero. This project is kept separate from the differently described cold-repair work in the narrative; matching by site and capacity alone is insufficient.
- Project budget / 2025 / project disclosed
- RMB 880,943,600
- Engineering progress / 2025 / project disclosed
- 100%
- Transferred to fixed assets / 2025 / project disclosed
- RMB 746,121,169.87