The Tongxiang expansion is described as a combined 80,000-plus-20,000-tonne alkali-free glass-fiber furnace drawing line. The operating narrative dates formal production to 18 March 2006, also states an ignition-and-production date of 8 January, and says design output was reached on 1 May and exceeded by 10%. These are the issuer’s differently labelled milestones, not a reconstructed single start date or measured full-year utilization. It reports 83,000 square metres of building area and describes oxygen combustion in the melting furnace and forehearth, large bushings with multiple drawing paths, in-line chopping and automated logistics. Page 14 prints investment as 99,901 units of CNY 100 million, whereas the specific investment section on page 20 prints 99,901 units of CNY ten thousand, equivalent to CNY 999.010 million. Both original pages have been checked. The latter amount is presented as the project-specific investment disclosure, with the contradictory narrative unit explicitly retained; no inferred correction is made to the original field or historical snapshot. Separately, construction project 210, explicitly labelled the 80,000-plus-20,000-tonne line, transferred CNY 834.642 million into fixed assets in FY2006. That accounting transfer is not the project’s total investment or cash paid during the year. The structured investment field records only the specific disclosure on page 20. It is not an independently reconciled project budget, a substitute for cash expenditure or a correction of the contradictory page 14 unit.
- Reported project total investment / 2006 / tongxiang 80kt plus 20kt project specific investment fy2006
- RMB 999,010,000