The Tongxiang 120,000-tonne alkali-free glass fiber tank-furnace drawing project entered production on 8 June 2007, following construction started in September 2006. The report describes large-unit drawing, oxygen combustion in the furnace and forehearth, multi-filament bushing processes, and in-line chopped strands. The same site, scale, product and construction start link this commissioning observation to the prior-year project. Claims that it was the largest and most advanced line are management assessments, not independently verified rankings.
At a glance
- Record type
- Project
- Earliest source in this dossier
- FY2006
- Latest source in this dossier
- FY2007
- Company
- China Jushi / 600176
Read the dated construction and operating milestones below. An installation stage or an engineering-progress percentage does not establish actual production. A programme and its component lines may describe the same capacity at different levels.
Location and identification
Exact physical address and coordinates have not yet been verified for this record.
Verified site coordinates: unavailable. No city-centre point is displayed as a plant location.
The following sections retain the full available English descriptions and their source context. Associated business context describes its named product or base.
FY2007 / Disclosed developments
FY2006 / Disclosed developments
A 120,000-tonne alkali-free furnace project started construction in September 2006. The filing describes large-unit furnace drawing, oxygen combustion in the furnace and forehearth, multi-filament bushing processes, and in-line chopped strands. Its construction schedule was forward-looking at the time of the discussion. This is an additional Tongxiang expansion, identified separately from the 80,000-plus-20,000-tonne project that had already entered production.
Sources and scope
What this guide establishes
- Reporting years identify the source filings. Actual event dates are retained in the text and may differ from the reporting year.
- The latest disclosure year for this object is not confirmation of its current operating status. Coverage is selected, not an exhaustive account of every report.
- Capacity, output, sales, construction progress and expenditure are separate measures. Programme and component capacities are not added together.
- Company contact addresses are location leads. They do not establish exact plant boundaries or the footprint of individual projects.
Chinese / A-share / Chinese Accounting Standards / Published 2007-04-12
PDF SHA-256: 476dbc0ea36f08137f89d4e316f94a0a71877f9ac12ef3672c71bd63c0306cf9
Chinese / A-share / Chinese Accounting Standards / Published 2008-03-05
PDF SHA-256: 981361898a8b1c99eebbe0ca8b7d922b226b9c2151636b6d30203639683acdb9