The 120,000-tonne alkali-free line energy-saving upgrade was marked complete. The table gives a project amount of RMB 162.0476 million and cumulative investment of RMB 160.0326 million. The project is related to the existing line through its explicit capacity and upgrade scope, while remaining a separate investment activity from the original furnace construction. A completed upgrade is not added to group capacity as another 120,000-tonne line.
The 120,000-tonne alkali-free line energy-saving upgrade is linked to the existing project record by its full upgrade description, reporting context and CNY 162,047,600.00 budget, which matches 16,204.76 ten-thousand CNY in the board table. The engineering table reports CNY 70,335,836.85 of current additions, CNY 361,896,453.08 transferred to fixed assets, 100% progress and a 72.49% investment-to-budget ratio. Its opening balance and transfer exceed the printed budget, and these figures do not provide an internally complete budget reconciliation. The original numbers are retained without enlarging the budget or changing the reported ratio. The board table's cumulative investment of 16,003.26 ten-thousand CNY is a different table measure, not an automatic reconciliation to the transfer. This activity remains separate from the 100,000-to-120,000-tonne cold-repair upgrade whose budget is 20,002.27 ten-thousand CNY. Matching final capacity alone does not justify merging the two project records or adding an entire new 120,000-tonne line to group capacity. Actual output, energy savings and precise project coordinates remain undisclosed here.
- Project budget / 2014 / reported engineering row
- RMB 162,047,600
- Annual construction additions / 2014 / reported engineering row
- RMB 70,335,836.85
- Project transfer to fixed assets / 2014 / reported engineering row
- RMB 361,896,453.08
- Reported investment-to-budget ratio / 2014 / reported engineering row
- 72.49 percent
- Engineering progress / 2014 / reported engineering row
- 100 percent