The 80,000-tonne-per-year alkali-free glass-fiber furnace-drawing line was the second component of the Jiujiang 150,000-tonne programme. It entered production in July 2010, after the first component in February. Its disclosed total investment was CNY 991,753,800, converted from the table amount of CNY 99,175.38 in ten-thousand-yuan units. The two component amounts are distinct reported investment totals; neither is an annual operating cost or independently identified annual cash outflow. This project continues the existing Jiujiang component record. The programme total is the sum of the two nominal line capacities, not a third additional line to add again. Annual production, utilization, fiber-grade mix and customer delivery are not separately quantified for this component in the cited project disclosure.
- Reported project total investment / 2010 / jiujiang 80kt line reported total
- RMB 991,753,800