SINOFILINGS / BUSINESS LIBRARY600176 / PUBLISHED
Project dossier / object-dossiers-v1

Jiujiang 20,000-tonne environmental glass fiber line

Project / Background, reported developments and evidence

Selected disclosures assembled into a continuing object history. Associated business context retains its own company, product or site scope. Source-page links provide optional verification; the English account is intended to stand on its own.

Source reporting periods through 2010-12-31 / Company library through 2025-12-31
Content version 30 / deea6484e3c3 / PUBLISHED

At a glance

Record type
Project
Earliest source in this dossier
FY2010
Latest source in this dossier
FY2010
Company
China Jushi / 600176

Read the dated construction and operating milestones below. An installation stage or an engineering-progress percentage does not establish actual production. A programme and its component lines may describe the same capacity at different levels.

Location and identification

Exact physical address and coordinates have not yet been verified for this record.

Verified site coordinates: unavailable. No city-centre point is displayed as a plant location.

The following sections retain the full available English descriptions and their source context. Associated business context describes its named product or base.

FY2010 / Disclosed developments

Open FY2010 company review

The Jiujiang energy-saving and environmental furnace-drawing line had a nominal annual glass-fiber capacity of 20,000 tonnes and entered production in July 2010. Its disclosed total investment was CNY 242,464,000, converted from CNY 24,246.40 in ten-thousand-yuan units. It is a separate named line from the 70,000- and 80,000-tonne components of the other Jiujiang programme, even though the second large component entered production in the same month. The existing 20,000-tonne project record preserves that distinction. The energy-saving and environmental description is the issuer label; the cited project row does not quantify this line's energy consumption, emissions reduction, annual output, customer deliveries or revenue. Total investment, nominal annual capacity and the disclosed production-start month are retained as different measures rather than combined into an estimate of FY2010 output or earnings.

Sources and scope

What this guide establishes

  • Reporting years identify the source filings. Actual event dates are retained in the text and may differ from the reporting year.
  • The latest disclosure year for this object is not confirmation of its current operating status. Coverage is selected, not an exhaustive account of every report.
  • Capacity, output, sales, construction progress and expenditure are separate measures. Programme and component capacities are not added together.
  • Company contact addresses are location leads. They do not establish exact plant boundaries or the footprint of individual projects.
FY2010 full annual report ↗
Chinese / A-share / Chinese Accounting Standards / Published 2011-03-18
PDF SHA-256: 915a3f5d8123cd46cb97ff324ddfdb4df1604303bfc4b9c3030b8f5abdd7bdb8