Proposed Indian glass fiber manufacturing base

Project / Background, reported developments and evidence

Selected disclosures assembled into a continuing object history. Associated business context retains its own company, product or site scope. Source-page links provide optional verification; the English account is intended to stand on its own.

Source reporting periods through 2020-12-31 / Company library through 2025-12-31
Content version 30 / deea6484e3c3 / PUBLISHED

At a glance

Record type
Project
Earliest source in this dossier
FY2017
Latest source in this dossier
FY2020
Company
China Jushi / 600176

Read the dated construction and operating milestones below. An installation stage or an engineering-progress percentage does not establish actual production. A programme and its component lines may describe the same capacity at different levels.

Location and identification

Exact physical address and coordinates have not yet been verified for this record.

Verified site coordinates: unavailable. No city-centre point is displayed as a plant location.

Reported measurements

Only measurements attached to this record are shown. Values retain their original reporting scope; rows are not summed into an asset total.

MeasureValuePeriod / scopeSource
Project budget245,558,900 USD2017-12-31india proposal / india proposalFY2017, p. 136

The following sections retain the full available English descriptions and their source context. Associated business context describes its named product or base.

FY2020 / Disclosed developments

Open FY2020 company review

The Indian project continued design optimisation. Management said construction would begin at an appropriate time after overseas pandemic risks became controllable. This is a conditional plan, updating the pre-construction preparation in 2019. No construction-start or production milestone is assigned, and no precise future commissioning date is inferred.

FY2019 / Disclosed developments

Open FY2019 company review

Preparatory work for India continued, including surveys, preparation, approvals and design before construction. Management described the prospective facility as a third overseas manufacturing base. The statement remains prospective: preparatory work is not a construction start or an operating factory, and the report does not provide a committed commissioning date in this passage.

FY2017 / Disclosed developments

Open FY2017 company review

The report says the Indian project was progressing according to plan. In the same passage, Egypt phase III is explicitly described as producing and the United States project as under construction. The India statement gives less detail: no commissioning date, line capacity or producing-factory milestone is established here. It therefore remains a separate proposed overseas manufacturing project with an unresolved schedule.

The filing proposes a 100,000-tonne-per-year alkali-free glass-fiber line in phase II of the Talegaon industrial zone, Pune, Maharashtra, India. It describes a proposed company with a provisional name, a two-year construction period and total investment of USD 245,558,900, printed as 24,555.89 ten-thousand US dollars. Management describes the project as being advanced and includes it in the following-year programme; that is not evidence of a commissioned factory. The proposed zone and city are retained as the issuer’s location statement, without assigning a verified street address or coordinates. The dollar proposal must not be added directly to the renminbi construction budgets, and a two-year schedule is not a verified completion date.

Project budget / 2017 / india proposal
245,558,900 USD

Sources and scope

What this guide establishes

  • Reporting years identify the source filings. Actual event dates are retained in the text and may differ from the reporting year.
  • The latest disclosure year for this object is not confirmation of its current operating status. Coverage is selected, not an exhaustive account of every report.
  • Capacity, output, sales, construction progress and expenditure are separate measures. Programme and component capacities are not added together.
  • Company contact addresses are location leads. They do not establish exact plant boundaries or the footprint of individual projects.
FY2017 full annual report ↗
Chinese / A-share / Chinese Accounting Standards / Published 2018-03-20
PDF SHA-256: 2ad4170565636643a4bfb947742953ed6d3adb848eab77a0efadabbf29b605c8
FY2019 full annual report ↗
Chinese / A-share / Chinese Accounting Standards / Published 2020-03-23
PDF SHA-256: 872b8cdc952da4386c152b9ae2b62bea426b324b15db58d4ec3b7df86ecaf2f5
FY2020 full annual report ↗
Chinese / A-share / Chinese Accounting Standards / Published 2021-03-20
PDF SHA-256: cbba64c59d36a001fa9b73e9e150f68b414bd6c2f8a3ccbc4e075ab91628813d