Egypt phase III, 40,000 tonnes per year

Project / Background, reported developments and evidence

Selected disclosures assembled into a continuing object history. Associated business context retains its own company, product or site scope. Source-page links provide optional verification; the English account is intended to stand on its own.

Source reporting periods through 2017-12-31 / Company library through 2025-12-31
Content version 30 / deea6484e3c3 / PUBLISHED

At a glance

Record type
Project
Earliest source in this dossier
FY2016
Latest source in this dossier
FY2017
Company
China Jushi / 600176

Read the dated construction and operating milestones below. An installation stage or an engineering-progress percentage does not establish actual production. A programme and its component lines may describe the same capacity at different levels.

Location and identification

Exact physical address and coordinates have not yet been verified for this record.

Verified site coordinates: unavailable. No city-centre point is displayed as a plant location.

Reported measurements

Only measurements attached to this record are shown. Values retain their original reporting scope; rows are not summed into an asset total.

MeasureValuePeriod / scopeSource
Annual production capacity40,000 tonnes/yearFY2017 filing; value date not structuredglass fiberFY2017, p. 11
Project budgetRMB 673,994,8002016-12-31construction note / construction noteFY2016, p. 89
Construction in progress at year-endRMB 161,930,881.052016-12-31construction note / construction noteFY2016, p. 89
Issuer-reported investment-to-budget ratio24.03 percent2016-12-31construction note / construction noteFY2016, p. 89
Engineering progress25 percent2016-12-31construction note / construction noteFY2016, p. 89
Annual production capacity40,000 tonnes/yearFY2016 filing; value date not structuredglass fiberFY2016, p. 9

The following sections retain the full available English descriptions and their source context. Associated business context describes its named product or base.

FY2017 / Disclosed developments

Open FY2017 company review

The third Egyptian phase, a 40,000-tonne-per-year high-performance glass fiber furnace-drawing line, formally entered production in 2017. This is the operating update to the construction and expected completion described in the 2016 report. Its phase label and capacity distinguish it from the two earlier 80,000-tonne projects. The passage does not give this line's realised output, utilisation or a full year of sales.

Annual production capacity
40,000 tonnes/year

FY2016 / Disclosed developments

Open FY2016 company review

The third Egyptian line is a 40,000-tonne high-performance glass fiber project, with construction reported to have started in May 2016. The important-construction table reports a CNY 673,994,800.00 budget, CNY 161,930,881.05 of additions and closing construction, a reported investment ratio of 24.03% and engineering progress of 25%. Funding is described as own funds and borrowing. A separate narrative gives total investment of 10,995.02 ten-thousand US dollars and an approximate one-year construction period, while management expected completion and production in the second half of 2017. These are source-specific currency and timing disclosures; the English account does not invent an exchange-rate conversion, treat the different schedules as actual commissioning, or add the planned capacity to 2016 operating output. A shared Egyptian base does not merge the phase with the two 80,000-tonne lines.

Project budget / 2016 / construction note
RMB 673,994,800
Construction in progress at year-end / 2016 / construction note
RMB 161,930,881.05
Issuer-reported investment-to-budget ratio / 2016 / construction note
24.03 percent
Engineering progress / 2016 / construction note
25 percent

Egypt phase III was launched in 2016 with stated capacity of 40,000 tonnes of high-performance glass fiber per year. Construction was reported to be progressing, with completion and production expected in the second half of 2017. This is a separate phase from both existing 80,000-tonne lines. The smaller capacity and explicit phase identifier prevent a shared Egyptian address from causing the three projects to be merged.

Forward-looking planFY2016 annual report, p. 9 ↗
Annual production capacity
40,000 tonnes/year

Sources and scope

What this guide establishes

  • Reporting years identify the source filings. Actual event dates are retained in the text and may differ from the reporting year.
  • The latest disclosure year for this object is not confirmation of its current operating status. Coverage is selected, not an exhaustive account of every report.
  • Capacity, output, sales, construction progress and expenditure are separate measures. Programme and component capacities are not added together.
  • Company contact addresses are location leads. They do not establish exact plant boundaries or the footprint of individual projects.
FY2016 full annual report ↗
Chinese / A-share / Chinese Accounting Standards / Published 2017-03-21
PDF SHA-256: aa002910e2f04f6c6a30d3195854c189d363d9f2ad18ff831c5e2a2abbb7b4c2
FY2017 full annual report ↗
Chinese / A-share / Chinese Accounting Standards / Published 2018-03-20
PDF SHA-256: 2ad4170565636643a4bfb947742953ed6d3adb848eab77a0efadabbf29b605c8