The project table identifies an upgrade to the packaging-material workshop of Jushi Group Chengdu. It gives a project amount of 7,990 ten-thousand CNY, annual investment of 1,224 ten-thousand CNY and cumulative investment of 6,821 ten-thousand CNY, and marks the project unfinished. This is a packaging-support project, not an additional glass-fiber furnace or a stated increment of yarn capacity. The table does not give a physical address, completion date, workshop output or savings. A separate project identity preserves the disclosed operator and activity without merging it into the Chengdu 50,000-tonne upgrade or 60,000-tonne conversion merely because they share a city.
- Project budget / 2014 / packaging workshop upgrade
- RMB 79,900,000
- Annual project investment / 2014 / packaging workshop upgrade
- RMB 12,240,000
- Cumulative project investment / 2014 / packaging workshop upgrade
- RMB 68,210,000
The Chengdu packaging-material workshop upgrade remained unfinished in the board investment table. Its budget of 7,990 ten-thousand CNY matches the CNY 79,900,000.00 engineering budget. The engineering table reports current additions of CNY 12,425,835.86, CNY 32,764,179.66 transferred to fixed assets, closing construction in progress of CNY 35,627,184.88 and 85.6% engineering progress. The board table separately gives current investment of 1,224 ten-thousand CNY and cumulative investment of 6,821 ten-thousand CNY. The source does not provide a complete bridge between the two annual investment measures. A closing construction balance is neither total spending since project inception nor the same as equipment already transferred to fixed assets. Packaging is supporting activity, not a newly disclosed glass-fiber furnace or a tonnage addition. The existing board budget and investment fields remain, while engineering figures keep their separate scope and evidence. No warehouse-equipment prepayment or finance-lease deposit is automatically assigned to this project merely because it also supports production.
- Annual construction additions / 2014 / reported engineering row
- RMB 12,425,835.86
- Project transfer to fixed assets / 2014 / reported engineering row
- RMB 32,764,179.66
- Construction in progress at year-end / 2014 / closing cip table
- RMB 35,627,184.88
- Engineering progress / 2014 / reported engineering row
- 85.6 percent